| |
|
Following a
series of lively corporate receptions on Thursday evening,
the
Spotlight! 2004 event took off with a start early on
Friday, September 24 at the Sheraton Four Points
in Ann Arbor, MI. Sixteen teams of diligent students put
their best feet forward to
showcase
their summer projects and to compete for a total of $24,500
in scholarship awards.
Each team presented its project results to an audience of
corporate
representatives, students, alumni and faculty. Judges from
the manufacturing industry evaluated
the projects on the basis of scope, implementation, impact,
overall presentation skills and other criteria to determine
the winners.
TMI congratulates
all of the student teams and sponsors for their support
and participation in the
2004 summer projects and the Spotlight! event.
We look forward to working with you on summer 2005 Team
Projects.
2004 Project Team Pictures
Click on the company name below to see a picture of the 2004
Project Team!
Click here to view the Spotlight! 2004 Project Book (PDF)
Spotlight!
2004 Winners
First
Place: Pfizer, Inc. - David
Portner and Nari TenKley gave the winning presentation of
their 14-week summer project titled "20% Global Capacity
Improvement Saves $50 Million." Each team member was
awarded a $4,500 scholarship.
Second
Place: Alcoa, Inc. - Jason
Clark, Raul Quevedo and Mohan Radhakrishnan came in second
place for their project titled "Improved Delivery
Performance through Product Leveling." Each team member
was awarded a $3,500 scholarship.
Third Place: McKinsey & Company
- Jacky Sung and Pinar Yaprak took third place with their
project titled "An Operational Transformation in the
Healthcare Industry." Each team member received a
$2,500 scholarship award.
Below are the project descriptions of the winning teams. For
a complete list of all sixteen participating companies and
project descriptions, please click on the link above for the
Project Book.
Pfizer, Inc.
"20% Global Capacity
Improvement Saves $50 Million"

Student Team
David Portner - Dual MBA/MEM (Master of Engineering in
Manufacturing)
Nari TenKley - EGL (BSE-IOE/MSE-IOE)
Project Champion
Michael V. Ganey - VP, Worldwide Pharmaceutical
Sciences, Global Supply Chain
Project Supervisor
Edward Kobelski - Vice President, Groton Supply Chain
Brian Swierenga - Associate Director, Global Supply Chain
Faculty Advisors
Izak Duenyas - Business School
Tassos Perakis - College of Engineering
The Pfizer TMI team increased the worldwide manufacturing
capacity of Pfizers kilo labs by more than 20% without
the need for any significant capital expenditures. This
increase in capacity has saved Pfizer the need to construct
an additional kilo lab manufacturing facility, which would
have cost approximately $50 MM.
The kilo lab facilities produce the first bulk quantity of
a prospective drug for toxicology testing and Phase I
clinical trials in humans. Since the kilo lab is the first
bulk manufacturer of a prospective drug and the first bulk
production drives the future development timeline, the kilo
labs speed and efficiency is a critical factor for the
remainder of the 10-15 year timeline before a drug hits the
consumer market. Within the kilo lab, there is also the
significant challenge of merging research with
manufacturing, as each production request is often a new
compound, never seen before in any of the manufacturing
facilities. This job-shop type of manufacturing environment
proved to be challenging in terms of data collection, lean
improvements and organizational design.
The TMI team offered a fresh perspective on the
manufacturing process, which is anything but traditional.
The process is inherently risky, as the scale-up in
production volume can introduce complications that cannot be
foreseen in laboratory investigations. Each new substance
uses unique raw materials and procedures, making the
variability with respect to processing time very large.
The team also examined the objective of increasing global
kilo lab capacity by 20% from several different perspectives
including: facilities and equipment, strategic manufacturing
and development, production planning and scheduling,
organizational design, lean principles, and continuous
improvement. The teams recommendations were global in
nature, for application in Groton, CT and Sandwich, UK, and
will serve as the template for organizational design in the
Ann Arbor, MI facility currently under construction.
Overall, the team showed Pfizer how to incorporate
traditional manufacturing disciplines in a non-traditional
production environment.
back to top
Alcoa, Inc.
"Improved Delivery Performance through Product Leveling"

Student Team
Jason Clark - Dual MBA/MSE-IOE
Ral Quevedo - EGP (Master of Engineering in Manufacturing)
Mohan Radhakrishnan - EGP (MSE Industrial & Operations
Engineering)
Project Liaison/Host
Dave Hoffman - Alcoa Business System Manager
Project Champion
Roy Dirkmaat - Director of Operations
Project Supervisors
Leslie Shuman - Alcoa Business System Director
Project Coordinator
Steve Bright - Alcoa Business System Specialist
Faculty Advisors
Eric Svaan - Business School
William W. Schultz - College of Engineering
Alcoa Mill Products-Lancaster operates in the competitive
$90 billion U.S. aluminum alloy market, a very demanding
customer service industry. In order to maintain and improve
their current market position Alcoa-Lancaster is working to
manage the variability of their 22,000 unique products,
customer demand, scheduling, and inventory systems.
Alcoa uses "on-time" delivery as its key performance metric,
which is a significant contributor to a healthy relationship
with its customers. An in-depth analysis of the production
system and its various support organizations indicated that
the primary delivery issue was not manufacturing or capacity
based, but rather was a result of significant demand and
schedule variation. The team hypothesized that the primary
cause was attributed to Alcoas current booking and
scheduling system. The system provides no leveling of
production requirements, forcing significant fluctuation in
machine utilization. In addition, the system is based on a
push philosophy, resulting in departments blindly
producing to a task based priority requirement regardless of
capacity or customer need.
In order to approve the hypothesis the team ran three shop
floor tests. These tests focused on three primary
principles: 1) generate level demand to the primary process
centers, 2) create shop floor visibility of demand and
production, and 3) ensure that a clear production signal is
generated from customer to supplier. This new pull based
philosophy resulted in the discovery of conflicting
performance metrics as well as substantial early production
at the expense of on-time requirements, and backlog.
Immediate action was taken to remedy the problems and a
continuous improvement process was implemented to ensure
sustainable change.
These actions resulted in two important improvements in the
performance of Alcoas current production system:
Material on-time to packing increased approximately 20%
By the fifth week of implementation, the promise
performance to the customer had increased
approximately
3-5%.
Since the implementation was initiated while the team was in
place, there is a high confidence level that the
implementation will yield the following returns:
Sustainable on-time delivery of material to customers of
90% or higher by year-end.
An estimated net decrease in inventory of approximately
12%. This net decrease by volume is
comprised of a 27%
decrease in work-in-process inventory, a 21% decrease in
finished goods
inventory, and a 5% increase in raw material
stores.
The expected return on the implementation of the pull
strategy is approximately $30 million
over a 3 to 5 year
period and a month-to-month improvement value of $1 million
over the same
period of time.
The estimated return on capital after preliminary
implementation is expected to increase from
approximately
10% to approximately 18% over a 3 to 5 year period.
back to top
McKinsey &
Company
"An Operational Transformation in the Healthcare Industry"

Student Team
Li-Yuan (Jacky) Sung - MBA/MC
Pinar Yaprak - EGL (BSE-IOE/MSE-IOE)
Project Liaisons
Daniel Woolson
Project Supervisors
Mike Nolte
Ed Stout
Kenji Asakura
Faculty Advisors
Ted OLeary - Business School
Wei Lu - College of Engineering
McKinseys client is one of the largest healthcare providers
in the U.S., owning nearly 100 acute care hospitals. In
recent years, the client has faced increasing challenges to
maintain high quality and profitability. As a result,
McKinsey & Company was invited to help perform a quality
transformation enabling the client to provide better
customer service and decrease its costs.
The TMI team joined McKinsey in helping the operational
transformation, primarily using lean manufacturing
principles. Although lean production is a well-developed
concept in the manufacturing industry, it is very applicable
and yet relatively new to the healthcare industry.
In order to build the clients transformation capabilities,
the TMI team designed lean operations training modules to
deliver essential skills to regional and hospital leaders,
allowing quick implementation of the transformation program
at each hospital. Additionally, the team designed a pharmacy
module that describes target areas for improvement. The team
also developed an excel-based tool used to effectively
monitor the progress of the improvements on a daily basis.
In addition to developing promotion and control mechanisms
at the corporate level, the TMI team also helped lead
implementation in the hospitals. The team assessed the
current performance through benchmarking metrics, discovered
areas requiring improvement, and launched many targeted
initiatives. Specifically, the team reduced patient waiting
time in the radiology department, improved first case start
delays in the operating room, decreased turnover time in the
operating rooms, and significantly improved the lead time
between a patient discharge and the time the room is ready
for the next patient.
These initiatives significantly increased patient
throughput, improved operational effectiveness, and enhanced
patient satisfaction. By involving both planning and
implementation stages at the corporate and hospital levels,
the TMI team not only created tangible impact on the
hospitals, but also built a foundation for sustainable
long-term improvement.
back to top
Return to Main Spotlight! Event
Page
|